Soundview Landing Building C
Site clearance starts
Demolition Begins
Environmental Remediation Performed
Final buildings reduced to rubble
Stormwater Retention System Installed
Foundation walls take shape
Mayor Rilling, HUD Director Suzanne Piacentini and NHA Executive Director Adam Bovilsky make a site visit
Foundation rises along Raymond St.
Concrete Pump used to pour foundation walls
East Wing Elevator Shaft Erected
Concrete mixers Used for Concrete Block elevator shafts
Future lobby and Resource Center in building C
Elevator Shaft and Support Columns Done
FRAC Tank used to control contaminated groundwater
Equipment used for subsurface sampling
Building footprint established
Masonry Joints Cut into Walls
Crane used for steel work
Steel I-Beams in Place
Concrete Finish Work Begins
Corrugated Steel Decking lifted into place
West elevator shaft nears completion
Steel decking installed
Steel framing complete for lobby and resource center
Safety railing installed prior to wood wall panel installation