Soundview Landing Building C

Site clearance starts

Demolition Begins

Environmental Remediation Performed

Final buildings reduced to rubble

Stormwater Retention System Installed

Foundation walls take shape

Mayor Rilling, HUD Director Suzanne Piacentini and NHA Executive Director Adam Bovilsky make a site visit

Foundation rises along Raymond St.

Concrete Pump used to pour foundation walls

East Wing Elevator Shaft Erected

Concrete mixers Used for Concrete Block elevator shafts

Future lobby and Resource Center in building C

Elevator Shaft and Support Columns Done

FRAC Tank used to control contaminated groundwater

Equipment used for subsurface sampling

Building footprint established

Masonry Joints Cut into Walls

Crane used for steel work

Steel I-Beams in Place

Concrete Finish Work Begins

Corrugated Steel Decking lifted into place

West elevator shaft nears completion

Steel decking installed

Steel framing complete for lobby and resource center

Safety railing installed prior to wood wall panel installation